Previous Page  10 / 24 Next Page
Information
Show Menu
Previous Page 10 / 24 Next Page
Page Background

10

Mining NZ

» Spring 2017

Gold » OceanaGold

North Wall project well on track

Karen Phelps

OceanaGold has constructed a noise bund using reconstituted topsoil material, which is currently located above the slip to the north east where it will remain until it is required for rehabilitation purposes.

Undertaking a project on unstable ground in a mine

located in an urban area with strict environmental

requirements while keeping the public happy may

sound pretty difficult. But that’s exactly the type of

project that has been taking place at OceanaGold’s

Waihi open cast mine.

Martha Mine had a well-documented large slip

on April 26, 2016, which saw two million tonnes

of rock fall. This large rock fall follows a smaller

rock fall on 2 April 2015 after which mining in the

open pit ceased. The current project, the North Wall

Interim Remediation Cutback, is to remove unstable

material in the north wall and stabilise it.

Kevin Storer, site services manager at

OceanaGold Waihi, says that due to the dynamic

nature of the north wall failure and its response

to mining, the stability designs and subsequent

remedial works have had to be modified ‘on-the-

run’ and as a result have had to change as work

progressed.

Any significant changes to design have been

peer reviewed and provided to stakeholders by

OceanaGold as necessary.

Kevin says that the west was the highest risk

area in terms of operation with long vertical drops

and unstable working conditions.

“The plan has been to continue to unload this

area of the wall by way of excavation above and

behind on stable ground out towards the unstable

areas. This left a safe area for operators to retreat

if sudden movement were to occur while drilling or

excavating.

“The current design to lower the west is de-

signed to achieve 60 degree batter angles with

five metre wide benches, depending on ground

conditions and levels of safety assessments as we

progress.”

Kevin says that the west area will join in with the

central area via a ramp and will open safe access to

the existing south perimeter road. The central area

of the failure has continued to fret away slowly and

the remedial works undertaken to-date have shown

a significant reduction in movement.

“Existing and new prisms have been installed

on the crest and have showed very little movement

before excavations got under way which indicated

this area to be relatively stable.

“As excavations have progressed, very hard

competent ground has been reached which is very

difficult to scale. Currently the bench is at final

design with a single bench cut which ranges from

15-20 metres wide as recommended by the lead

design consultant.”

He says to the east area of the failure a large

block has been showing creep into the failure area.

To help stabilise this block and prevent further

regression it needs to be unloaded, also from the

top.

“Currently the working bench will allow access

to the bottom level, however this has needed to be

redesigned as the ground conditions in the far east

are poor (saturated clay materials).

“Batters angles are 60 degrees immediately

around the eastern block, but are angled shallower

to 30-45 degrees in the east due to the weaker rock

mass. The width of each bench is five metres,”

explains Kevin.

Glenn Kiernan, general manager of Inline Drilling,

the company that is undertaking the drill and blast

component of the project, says that the project has

been particularly challenging as blasts need to take

place as close as 80 metres to the boundary wall.

Major risk assessments were undertaken

prior to the project getting underway and several

innovative methods of tackling the project devised.

He says that the fact that Inline Drilling had

experience working on the site for over 17 years

stood the company in good stead to come up with

the best solutions in conjunction with OceanaGold.

Two standard top hammer drilling rigs were

fitted with rotary drill heads to make the drilling

operations significantly quieter so only engine noise

was emitted. Local explosive companies were used

to gain the best cost effective and supply delivery

options to suit the varied challenges for each part

of the project.

Global Seismic Solutions provided the

Daveytronic electronic detonators which provide

extremely accurate inter-hole delay timing for better-

controlled blast induced vibration levels to ensure

the project adhered to mine consent conditions for

the project. Because smaller charge weights were

necessary when operating close to boundaries

Glenn says blast hole loading needed extreme

accuracy. The Orica Mining Services underground

mini loader emulsion pumping system provided

charge weight accuracies in 250 gram strokes.

While normally these units are used

underground, Glenn says that Orica Mining Services

got these certified for use on an open cast mine.

The Orica bulk emulsion product is also

non-fuming making the blasting on site more

environmentally friendly. On the lower benches

where higher charge weights were not a problem,

local supplier Prime Explosives supplied product

pumped from a 4WD bulk delivery truck.

Inline Drilling was the overall drill and blast

manager therefore streamlining the supplier

client management process allowing the client

to negotiate their own explosive pricing direct

from suppliers of their choice. Inline Drilling then

provided overall expertise and advice specific to

implementation of these tasks which has required

significant degrees of discipline and accuracy due

to the compliance sensitive nature of the tasks.

“We have to be extremely accurate in what we

do working so close to the boundary and unstable

Currently the bench is at final design with a single

bench cut which ranges from 15-20 metres wide as

recommended by the lead design consultant.”

areas on a project such as this. There is no room

for mistakes,” says Glenn.

Health and safety was a major focus and

included specialised procedures for anchoring the

drill rigs to the bulldozer such as escape plans,

how attachments were to be completed, daily

geotechnical assessments, spotters etc.

OceanaGold has been monitoring the north wall

using a radar system and other devices. The radar

provides important accurate information at every

stage of the project. In addition prisms monitored

the site along with a human ‘spotter’ observing and

searching for areas of movement.

A number of prisms were damaged as a

result of the North Wall slip and construction of

the Western Ramp and as a result OceanaGold

has progressively re-established a more robust

prism monitoring network. Precise levelling and

monitoring of ground conditions is another control

measure in and around the slip area, this as well as

the prism and radar monitoring of the slip area, will

continue to be carried out.

Although OceanaGold spokesperson Kit

Wilson says that mining within the pit will not be

undertaken in the coming years, the obligations

and procedures associated with an active mine site

remain in place and OceanaGold continues to be

responsible for the site.

The company has constructed a noise bund

using reconstituted topsoil material (approximately

12,000m3), which is currently located above the

slip to the north east where it will remain until it is

required for rehabilitation purposes.

The topsoil stockpile and base surface has been

surveyed to ensure minimum loss of material and

grassed for stability and visual effects.

The North Wall Interim Remediation Cutback

project is scheduled to be completed by the end of

August. The volume of the stockpile material during

the project has been estimated at approximately

130,000 cubic metres.

Kit says that with the complex nature of the

north wall failure, the company will continue to

monitor and further stabilise the wall if required

to mitigate any potential further regression to the

north.